Stephanie Myers | News-Herald
Greenback School construction foreman John Adams of Merit Construction describes the layout of the middle and high school at the new school, which is set to open by next January.
Amidst the recent chilly, dreary days, construction on the new
Greenback School is on track. Classes in the new school are scheduled to begin by next
January. Portions of the roof are up, the main entrance rotunda is taking shape and the brick
veneer is climbing the exterior of the new 145,300-square-foot facility, which sits adjacent to the
current 78,440-square-foot building. The new structure sits on 27.9 acres. Though the project is
a big undertaking at almost four acres under one roof, Merit Construction President and Project
Manager Bruce Bosse said the steel beams and concrete foundations are beginning to resemble a
school. "It's really going to be a beautiful building once it's done," Bosse said. Concrete
slab work is complete except on the second story, which is the high school wing. The middle school
will be housed underneath. Bosse said the slab work should be poured by the end of the
month. "There is still block work to lay. The second level, once that second slab is poured, then
we have to take the block work all the way up to the roof level, then of course there is steel that
goes up on top over that block work and then the roofing that goes on," Bosse said. "That will
probably be going on through spring. "While that is ongoing, we will still be doing finishes in
other parts of the area where we have already accomplished that," he said. Crews have been on
site since April. Bosse said sections of the school are further along than others, with some
being close to completion. "It's kind of a work in progress right now as far as seeing what the
end product will look like," he said. "There are some portions of the building you can already
visualize what the end product will look like. There are two colors of brick and many parts of the
building that brick is already completed." The multipurpose assembly area is "all dried in,"
meaning the drywall is up and the ceiling and some wall sections are coated with primer. "The
roof is on, but there are still glass and windows and the exterior walls are in the process of going
up," Bosse said. "There is an L-shaped area that wraps around. That area is kind of the shop,
kitchen-type area that is also now in the dry, which will allow for insulation and those things to
press on." The music and band room has a bit more work. Bosse said steel beams should be
installed next week with that roof going on shortly afterward. Skylights that will grace the
elementary school ceiling should be installed starting late next week. The elementary school is
broken into two wings running parallel. One wing will hold grades third through fifth, with the
other wing for pre-K through second grade. A playground/courtyard area will be fenced between the
two wings. "Then there is a whole variety of finishes: flooring finishes, some amount of drywall,
acoustical ceilings and that kind of thing," Bosse said. "Once we get into a little more decent
weather and the masonry contractor is done with his work, then we will go back to sidewalks. That
will probably be late spring, early summer before that will start." Loudon County Director of
Schools Jason Vance said he is excited as construction moves further along. "We won't have to have
kids in portable buildings," he said. The new school, which will hold about 900 students, is part
of a $43 million building program that includes a new Fort Loudoun Middle School and the recently
completed Philadelphia Elementary School cafeteria renovations. "Everything is going to be nice
and new, and it's going to work. It's just going to be conducive to learning. We're excited about
that. We think it will be good for the students, the teachers and for the community as a whole,"
Vance said. The new Greenback School will cost slightly less than $24 million and is on budget.
Constructing a new Fort Loudoun Middle School is budgeted for less than $17 million and the
Philadelphia cafeteria renovations came in at less than $1.5 million. Since joining Loudon County
Schools in 2004, Vance said building a new Greenback facility was deemed important. "We just
really felt, looking at the old school, it was time. The old school was out of date, and it seemed
like there was trouble in so many different facets with architectural trouble and electrical
trouble. The facility was overall out of date and run down. We felt it was appropriate to move
toward building a new school over there," Vance said. "To see one finally come to fruition is
amazing. I'm excited to be a part of the process." The current school was erected in 1939. As
far as the old building, its future is still up in the air. "That's still up for discussion at
this point," Vance said. "It will be nice if someone wanted to buy it from us. I don't necessarily
know what the market is for that sort of thing, but I think that is what we will try to do first is
put it up for sale and try to see how it goes."
NEWS-HERALD
A Tennessee Press Association Award Winning Newspaper ~ Serving Loudon and surrounding counties since 1885.
201 Simpson Road, Lenoir City, TN 37771 (865) 986-6581